The construction of 'flyover' at Gwarko in Lalitpur will begin in the first week of January. At present, Senior Divisional Engineer Saurabh Bajrarycha, spokesperson of Development, Development Center, will start construction in the first week of January.
The construction period of the flyover has been fixed for 14 months. Although the road in this area has been widened and made into 10 lanes, a flyover is going to be built to solve the problem of traffic jam. At present, this area has a four-lane main road, a service lane and beyond that, one lane each on both sides.
As vehicles are currently parked in the outermost lane, it should be removed and regular traffic should be allowed. By operating the lane, motorcycles can be operated.
The height of the flyover will be six meters, while a 280 meter long 'Yam' will be built towards Balkumari and a 175 meter long 'Yam' towards Satadobato. The total length of the flyover is 490 meters and the 'super structure' will be 35 meters. After the flyover is operational, the vehicles plying Mangalbazaar-Imadol-Mangalbaazar will pass under the bridge, while the vehicles plying on the ring road will pass over the bridge.
"Currently, the work of goods management is going on, probably the construction will start after 10 days. Since some goods are yet to be imported, the goods are being brought.” said Saurabh Bajrarycha._RSS